West Bend, WI – WE Energies has closed on approximately 20.1 acres in the Wingate Creek Business Center in the City of West Bend, Wisconsin.
The sellers wereZiegler/Bence West Bend, LLC and Stockhausen Business Center, LLC.
The property will be the location of WE Energies new $34.3 million, 60,000 square foot service center. This move shows a cost savings plan that will consolidate the current West Bend and Port Washington locations and provide a central hub.

Adam Williquette, President of American Commercial Real Estate, represented the seller of the Wingate Creek Business Center, and worked with the buyer on the transaction.
“This was a fun project. Originally, the Wingate Creek Business Center had two separate parcels for sale that were 11.772 acres and 5.7 acres separated by Wingate Street that were not large enough for the new development. We were able to find a creative solutionby negotiating 2 additional acres of adjoining land on a neighboring property as well as getting a portion of Wingate Streetvacated to meet the acreage needed for this facility.”, said Williquette.
This sale closes out the business park with all lots being sold. ACRE still has land available in the West Bend Corporate Center and is in the process of finalizing a TID to fully extend utilities to serve the remainder of that park.
About American Commercial Real Estate: ACRE was founded in 2018 by Adam Williquette. He has over 20 years of commercial real estate experience. ACRE concentrates on brokerage, development, management, and investment in all aspects of commercial real estate.
About American Companies: Together, American Companies are a full-service Commercial Design / Build / Develop / Real Estate firm which includes American Construction Services (ACS), American Architectural Group (AAG) and American Commercial Real Estate (ACRE). Since 1980, ACS and AAG have built a solid reputation through their expertise in construction management, architectural design and structural engineering.
ACRE was added in 2018 to round out their portfolio by offering property sales, leasing, management and investment services.
American Companies are based in West Bend, WI. They specialize in all aspects of commercial real estate.
At American Companies, “Our job is to allow you to do yours.”
West Bend, Wi – We Energies has filed a proposal with the Public Service Commission of Wisconsin to build a new service center in West Bend, WI.

According to We Energies Brendan Conway, the new facility would replace the current facility in West Bend that was built in 1966 and needs significant, expensive upgrades.
Click HERE to SUBSCRIBE to
FREE local news at
Washington County Insider on YouTube
The new building would also house employees and equipment that are currently at the Port Washington Service Center.
The proposed new service center will provide customers streamlined operations and improved response times during outages while eliminating safety hazards for employees.
Project Details and Project Area Information
The Project Site consists of an approximately 19.5-acre parcel situated in the Wingate Creek Business Center. Of this total parcel, approximately 13 acres are in between Trenton Road (East) and Stockhausen (West), and the remaining 5.7 acres are in the southwest
corner of the Business Center. The Project Site is currently zoned as M-2 Industrial District and B-1 Community Business District.
The Project Site is located in the northeast area of the City, a community with a population of approximately 32,000. The Project Site is within Wingate Creek Business Center. The borders include the following: to the northwest is a Piggly Wiggly grocery store, to the west is Culligan of West Bend, to the southeast is the Comar West Bend Plant, to the east is
Americraft of West Bend and to the northeast is a BP gas station and a Valvoline Oil Change Center. Residential parcels are in the vicinity of the Project Site; however, they are buffered by the grocery store and Highway 33.
Site work and construction are planned to begin in October 2025 pending Commission approval, with anticipated completion and occupancy by December 2026.
Key project milestones are outlined below:
January 2024: Submit application
November 2024: PSCW approval
May 2025: Bid project
June 2025: Award contracts
June 2025: Permitting
October 2025: Commence site work and construction
November 2026: Complete construction
December 2026: Relocate consolidated operations from WBSC
and PWSC
The existing WBSC and PWSC sites will remain operational until the new WBSC construction is complete, and occupancy is granted, at which time operations will be relocated and consolidated.
“We estimate the project will cost $34 million and see $110,000 in annual operation and maintenance savings compared to the other alternatives,” said Conway.

The filing with the state is below.