Construction update in Germantown, WI

July 5, 2023 – Germantown, WI – A few updates regarding the ongoing road construction in Germantown.

Germantown

Eastbound County Line Rd over I-41 is scheduled to reopen the evening of Wednesday, July 5

Westbound County Line Rd over I-41 is scheduled to close the evening of Wednesday, July 5 for about 2 months

Freistadt Road bridge over I-41 is scheduled to reopen the evening of Friday, July 7, 2023.

Maple Road bridge over I-41 is scheduled to reopen the evening of Saturday, July 8, 2023.

Mequon Road bridge over I-41 (not Lannon Road which has the on/off ramps) is scheduled to close on Monday, July 10, 2023, for about 5 months

For more information about the project, go to https://projects.511wi.gov/41rehabilitation/

cast iron

Leave a Reply

Work or the content on WashingtonCountyInsider.com cannot be downloaded, printed, or copied. The work or content on WashingtonCountyInsider.com prohibits the end user to download, print, or otherwise distribute copies.

Subscribe

FREE local news at Washington County Insider on YouTube

Related Articles