Specialty packaging solutions and custom medical devices plant expanding in West Bend | By Paula Leach

November 10, 2020 – West Bend, WI  – Comar, a premier supplier of specialty packaging solutions and custom molded medical devices and assemblies is proud to announce the relocation and expansion of its West Bend, Wisconsin manufacturing site.

Comar, packaging

This represents the third major site expansion announcement by Comar in 2020.

Comar’s West Bend operation is moving into a 160,000 square-foot former plastic molding facility less than five miles from the current location, 910 Rusco Road.

The new building, 2845 Wingate St,                               will triple Comar’s local footprint and eventually house over $7 million of capital investment in high tonnage injection molding machines, large cavitation molds, and press side automation.

Mike Ruggieri, CEO of Comar, said, “The pandemic affecting our society has brought an unprecedented surge in demand for Comar’s rigid packaging, especially for disinfecting wipes used in hospitals, homes and institutions. We recognize the critical role our injection molding and blow molding solutions play in delivering essential supplies to the frontlines in the battle against COVID-19. This expansion shows our commitment to the fight and will position Comar to better meet demand while addressing the growth and service level needs of our customers. We will also be situated to support future injection molding and blow molding business opportunities and partnerships with our extensive floor space. ”

James Spalding, West Bend Plant Manager at Comar, adds “In addition to the capacity expansion, our team members are looking forward to the improved floor layout, new break rooms, dedicated training facilities, and the planned investments in employee development. We anticipate an enlargement in our team as Comar is actively recruiting to fill immediate openings for skilled technicians and shift operators for the plant.”

Comar expects to begin production at the new address on newly installed equipment in December 2020 and commence a full plant move during the first quarter of 2021.